Staffordshire County Council will begin work to install a new zebra crossing on St Edward Street in Leek from Tuesday 21 July. The scheme is part of Active Travel England's initiative to improve local infrastructure.
What the work includes
Installation will cover a zebra crossing, widening of the footpath on the eastern side, new dropped kerbs and tactile paving. The work also includes new belisha beacon poles with integrated lighting, resurfacing on the approaches to the crossing, and new and refreshed road markings.
A new uncontrolled crossing facility will also be provided on High Street, adjacent to its junction with St Edward Street, to improve safety and accessibility for pedestrians.
Timescale and disruption
Works are expected to take around three weeks to complete, with working hours between 7:30am and 4:30pm each day, weather permitting.
A temporary road closure will be in place on St Edward Street, affecting access from the Sheep Market and High Street junctions. A signed diversion will operate during this time. Access will remain available from alternative routes, and access to shops and emergency services will be maintained via these junctions where required.
Some footway closures will also be needed at times during the works, but alternative pedestrian routes will be provided throughout. Local businesses will remain open as usual, and access to properties and businesses will be maintained wherever possible.
Council statement
Patrick Allen, Cabinet Support Member for Highways at Staffordshire County Council, said: "This is an important scheme for the area that will provide a safer and more enjoyable environment for everyone who uses the town centre. The new designated crossing will also make it much more accessible for pedestrians, especially for people with disabilities and wheelchair users."
For updates on highways improvements and roadworks, residents can sign up to the county council's monthly newsletters.